December 10, 2021
 

Baraboo Project Update

The team at Americon Construction has been hard at work making sure that the new multi-family unit at 325 Lynn Street, Baraboo is on schedule.

It will be the most modern apartment community Baraboo as of 2022.  Located in the downtown area right on the Baraboo River, this facility will have well-appointed, open concept interiors featuring grand windows with breathtaking views, and apartments that have Keyless entry. Each unit equipped with either a private patio or balcony area, plus the building will have a 24-hour fitness center, an outdoor patio, and community room.

 
A completion date is estimated to be late May 2022, as tenancy is set to begin on June 1st.
 
 
November 13, 2020
(Tomah, Wi.)
 
The team at Americon Construction started a new project in Baraboo, Wisconsin this week.
 
The project that is now underway is a new multi-family apartment building.  This structure will consist of 66 units, encompassing an overall total of 112,000 square feet, 2 levels of underground parking, 4 stories of apartment living, a workout room, and a community room, which will be connected to a patio overlooking the Baraboo River (with natural gas grills on the patio).
 
The building is set-back off the river 75 feet, providing a great view for the residents inside this building. Baraboo is just minutes from Devil’s Lake, and only about 20 minutes from Wisconsin Dells.
Project Completion is estimated to be in 2021.